New Enterprises & Services Tower – 02

With an aim to rejuvenate and re-development of SEEPZ, the Authority is constructing NEST-2 building with approx. 375011.91 Sq. Ft. built-up area (01 Basement+Ground+6) as one of the major project.

The NEST-2 is primarily for Electronic Hardware & Software sector units which shall be relocated from existing SDF-1. Hence the Design and Built process shall incorporate close consultation with the existing SEZ units of Electronic Hardware & Software Sector to be relocated from SDF1 to NEST-2.

SEEPZ-SEZ, SEEPZ SEZ proposes to have the project executed on EPC turnkey basis through a reputed Indian entity fulfilling the specified eligibility criteria.

Contracting services shall include Construction of New Enterprises & Services Tower (NEST) – 2 which tentatively comprises of 1 Basement + Ground + 6 floors.

The scope shall include but not limited to all Civil & Structural works, Architectural, Interior design, Fire Fighting, Internal & External Electrical works, Fire alarm, lift, plumbing & drainage, sanitary fixtures, external infrastructure works, external services, etc.

  • 01.07.2022
    Appointment of Project Management Consultant (M/s WAPCOS Ltd)
  • 29.11.2022
    Published of Request for Proposal for EPC Developer (Design & Build) For Construction of New Enterprises & Services Tower (Nest)-2 at SEEPZ-SEZ, Andheri (E), Mumbai, Maharashtra
  • 19.01.2023
    Award of Contract for EPC Developer (Design & Build) (M/s C K Infrastructures Ltd., Delhi)
  • 24.01.2023
    Appointment of PMC for EIA Study (M/s WAPCOS Ltd)
  • 19.03.2024
    Handover Project
  • 19-01-2023
    Award of Contract
  • 30-01-2023
    Mobilization at site
  • 01-04-2023
    Topo survey, Geotech investigation, Building design & approvals
  • 07-07-2023
    Excavation
  • 03-01-2024
    Building Core & Shell
  • 13-01-2024
    Brick work/Plaster Work
  • 25-02-2024
    MEP, Interior finishing, Elevators
  • 27-02-2024
    External Infrastructure
  • 28-02-2024
    Handover
  • 1. Geotechnical investigation done on- 14-02.2023
  •  
  • 2. The Design is in progress in consultation with Trade Members.
  •  
  • 3. The NOC for commencement of work from Airport Authority of India has been received.
  •  
Updated On: 05-Mar-2023