The Mega CFC is one of the key projects initiated by the SEEPZ Authority under the Ministry of Commerce with GJEPC as the nodal body for implementation, commencement and running of the project to enhance the capacity of the industry in manufacturing products utilizing cutting edge technology provide and impart training and skilling facilities thereof to boost gems and Jewellery exports from the country.
In his address about the Mega CFC, Shri Piyush Goyal said, “This public and private partnership that will be completed in a record time of 500 days right from conceptualization to commissioning will set a new example for the country, and the Mega CFC will be a jewel in the crown of the industry and India. Further, revamping of the SEEPZ will regain the glory of special economic enclave and it will serve as a golden gateway to the markets across India and boost global development. This is the time for action and speed, and I hope that the commendable efforts by the GJEPC and SEEPZ authority will see the Mega CFC project to reach to fruition. If the deadlines are met, the inauguration of the centre will coincide with the 50th anniversary of SEEPZ."
Vipul Shah, Chairman, GJEPC said, “The Mega CFC will be an iconic centre with facilities for cutting-edge technology, to support designing and manufacturing of Gem and Jewellery products. It will enhance the existing quality, productivity, domestic R&D, technological advancement, and cost-competitiveness. It will also include a training centre for imparting skill development courses to further enhance the skills of the artisans in the industry. The platform will help boost Gem & Jewellery exports from India.”
The facility will provide common manufacturing processes and related services to jewellery units. This will not only help to reduce the cost of production in a big way but also lead to the transfer of know-how amongst these units, thereby providing a competitive advantage to them.
The centre will provide access to a common pool of high-end capital-intensive state-of-art machines. It will provide a wide spectrum of ancillary services such as CAD CAM, electroplating, fire assaying, manufacturing, 3D metal printing, etc. along with providing consultancy, R&D and training. Mega CFC facilities will be made available at a reasonable rate not only to SEEPZ-SEZ units but also to factories outside the zone which will improve the output in terms of quality, productivity and yield of the finished jewellery.
Shri Shyam Jagannathan, Development Commissioner, SEEPZ and Shri CP Singh Chauhan, Joint Development Commissioner also spoke on the occasion and described how the mega CFC will help to grow the exports of gem & Jewellery out of SEZ to more than 15 billion US Dollars from its current output of 7 billion US dollars, in the next few years.
Milestone
-
12 March, 2022Award of Geo Technical Investigation Contract (M/s Renuka)
-
12 March, 2022Geo Technical Investigation and receipt of Final Report
-
25 March, 2022Removal of RCC Structure & felling of 22 Nos. of Trees
-
12 May 2022Appointment of Project Management Consultant for statutory Completion (M/s WAPCOS Ltd.)
-
1 July 2022Award of Contract for Design Consultancy (M/s Vijay Punjabi Consultant Pvt. Ltd.)
-
1 August 2022Finalization of Design of Mega CFC
-
30 August 2022Award of Contractor for Excavation and Shore pilling (M/s DB Infratech)
-
11 October 2022LOA issued to Building Contractor (M/s Hariom Projects Pvt Ltd)
-
14 October 2022Appointment of Project Management Consultant (M/s Meinhardt EPCM India Pvt. Ltd.)
-
16 October 2022Pre-construction
-
18 November 2022RFP For Façade Works (Uploaded on CPP Portal on 18th November 2022)
-
1 March 2023Completion of Building Core and Shell
-
02 March, 2023Interior Design Consultant onboarding & Designing Work with BOQ
-
16 March 2023Completion of Electrical, Firefighting and Plumbing
-
31 March, 2023RFP Tender bidding
-
31 March 2023Completion of External Infrastructure
-
1 April 2023Completion of Elevators
-
1 April 2023Completion of MEPF and Interior (Finishing) for Common Area
-
01 April 2023Completion of Finishing Works
-
10 April, 2023Interior Contractor onboarding & Mobilisation and Japproval of materials
-
27 April 2023Completion of Facade Works
-
30 April 2023Handover
-
14 May, 2023CIVIL WORK-Excavation & Slab Work-Basement+6 Floors & Terrace
-
01 June, 2023Procurement of Machines
-
21 June, 2023Installation of Façade
-
29 June, 2023Procurement & Installation of Chillers / AHU/ Lift Machines
-
04 July, 2023Interior of Service Corridor (Toilets, lifts passage)
-
20 August, 2023Interior Contractor Work
-
26 August, 2023Installation & Commissioning of Machines
-
27 August, 2023Handover of Project