New Enterprises & Services Tower – 01

With an aim to rejuvenate and re-development of SEEPZ, the Authority is constructing NEST -01 building with approx. 163221.95 Sq. Ft. built-up areas (01 Basements+Ground+6 Floors) as one of the major project

The NEST -01is primarily for Gem & Jewellery sector units which shall be relocated from existing SDF’s. Hence the Design and Built process shall incorporate close consultation with the existing SEZ units of G&J Sector to be relocated from SDF’s to NEST -01.

The project executed on EPC turnkey basis through a reputed Indian entity fulfilling the specified eligibility criteria.

Contracting services shall include Construction of New Enterprises & Services Tower 01 (NEST-01) which tentatively comprises of 1 Basement + Ground + 6 floors. The scope shall include but not limited to all Civil & Structural works, Architectural, Interior design, façade works, HVAC, Fire Fighting, Internal & External Electrical works, Fire alarm, access control, lift, plumbing & drainage, sanitary fixtures, external infrastructure works, external services, etc.

  • 01.07.2022
    Appointment of Project Management Consultant
  • 30.08.2022
    Published of Request for Proposal for EPC Developer (Design & Build) For Construction of New Enterprises & Services Tower – 01 (NEST -01) for Gems & Jewellery Units at SEEPZ-SEZ, Andheri, Mumbai, Maharashtra –
  • 16.11.2022
    Award of Contract for EPC Developer (Design & Build) (M/s Aashi Soluation)
  • 18-12.2022
    Geotechnical investigation done on
  • 27.12.2022
    Design Finalization & Submitted to SPA
  • 03.01.2023
    Ground Breaking Ceremony & Excavation Started
  • 25.01.2023
    Site Mobilization done on
  • 10-02-23
    Excavation Work
  • 03-03-23
    Up to Plinth Work
  • 04-04-23
    Basement 1 Slab
  • 16-04-23
    Ground Floor
  • 28-04-23
    1st Floor
  • 10-05-23
    2nd Floor
  • 22-05-23
    3rd Floor
  • 03-06-23
    4th Floor
  • 15-06-23
    5th Floor
  • 25.05.2023
    Completion of Building Core and Shell
  • 27-06-23
    6th Floor
  • 30.06.2023
    Building finishing works and services
  • 01-07-23
    Terrace Floor
  • 31-07-23
    Finishing work & Handover
  • 1. Excavation Work Completed
  •  
  • 2. The Design and other requisite documents was submitted to the Special Planning Authority/Chief Fire Officer.
  •  
  • 3. The NOC for commencement of work from Airport Authority of India has been received.
  •  
  • 4. GRIHA Consultant M/s Vishwas Kulkarni Environmental (VK:e) is appointed by contractor.
  •  
Updated On: 05-Mar-2023